Subject: 77 MW SIEMENS ROLLS ROYCE COMBINED CYCLE POWER PLANT BASIC SCOPE OF SUPPLY


Date: 3/5/2024 2:17:43 PM

Details: Reviews 0

MAIN EQUIPMENT LIST

Plant design Capacity : 80.99 MWm / 77.13 MWe

Gas Turbine : Purchased but not installed Rolls Royce Trent 60 DLE / USA 63.07 MW

Steam Turbine : Purchased and installed. Siemens AG 30 bara. 17.92 MW

HRSG : Purchased and installed. Nooter/Eriksen

ACC : GEA

ACC Steel Structure : Produced and installed

Raw Water Tank : Produced and installed

Demineralized Water Storage Tank: Produced and installed

Service Water Tank : Produced and installed

Switchyard and transformers: Purchased and installed by Alstom Energy, Connected to 154 kV Line.

Power Line : Power line distance is 1.200 mt and Provisional Acceptance completed

Natural Gas Line : Distance is 2.200 mt and ready for acceptance by grid operator

RMSA Station : Ready for acceptance by gas supplier

Demin Water System : Aquamatch. Installed

DCS : Foxboro – not installed but manufactured and kept in supplier warehouse

MCC : Manufactured but not insalled and kept in supplier wareshouse

Pumps and valves : Ready to deliver in supplier warehouse

Oil Cooler : Kelvion. Installed

Natural Gas Simplex Filter: Eltacon Holland. Installed

Diesel Generator : Purchased but not installed. Generator 880 kVA.

Air Compressor : Atlas Copco

Cables : HES - LAPP - Helukabel - Anixter

Status At Site : All listed equipment are at site. Installation started at May 2017 but stopped

Complete quote for de-commissioning and re-commissioning on request

To see the contact details please Login or Register
Contact Name:
Company Name:
Mobile Phone:
Phone:
Fax:
Country:
E-Mail:
Web:

Comments      Add New Message

Leave a reply

Replace the security code

We use cookies to improve your experience. By continuing to use our site, you accept our Cookies, Privacy Policy,Terms and Conditions. Close X