1.1 Generator set manufacturing date (see photo) -2019
1.2 Operation time of the power station --2020
1.3 Power station composition includes:
1.3.1 Generator set (including unit body, +M control cabinet, +A control cabinet, GAS train)
1.3.2 Power Station supporting (including: Generator set, internal and air conditioning system, air
intake and exhaust system, external cooling water system and domestic water unit, external
silencer, external exhaust GAS boiler and SCR, gas compressor station and air compressor unit, steam turbine unit and lithium bromide equipment, domestic supporting electrical control box). 2 Quality status:
Electrical equipment and unit electrical components through long-term electric heating
maintenance, mechanical parts regularly crankshaft turning (start pre-supply oil pump)
2.1 generator set:
2.1.1 J620 gas engine
The engine and generator are jointly arranged on the same common base, the production date is
2019, and the operation time is about 4000 hours after the factory, and the appearance is good
(because the unit is arranged in the machine room). The components are complete. 2.1.2 leroy-somer generator
Because the automatic electrical heating maintenance, in good condition, the main components
are complete. 2.1.3 +M2 Control cabinet
It is installed on a common base and has complete internal components. 2.1.4 +A Control Cabinet
Arranged in the centralized control room of the equipment room, long-term power, good
condition, complete components. 2.1.5 GAS train
The original parts of the device, such as: check valve, solenoid valve, flow detector, pressure
sensor, etc. All are in good condition in the machine room. 2.2 Power Station supporting:
2.2.1 Cooling water system
External low temperature and high temperature air cooled coolers are arranged on the roof of
the equipment room, and the pipelines are respectively connected to the J620 unit through the
pumping station. 2.2.2 Silencer
Arranged in the silencer room of the equipment room, the smoke exhaust pipe first enters the
silencer, and then connects to the intake pipe of the external waste steam boiler through the
external wall. 2.2.3 External exhaust gas boiler and SCR: (8TON/ hour)
Arranged outside the machine room, with SCR purification system, divided into No. 1 and No. 2,
through the electronic control valve and three-way pipeline and smoke exhaust pipe and silencer
connected, step ladder directly. 2.2.4 The GAS compressor station and the air compressor unit are arranged in the oil storage
room in the equipment room and are in good condition. 2.2.5 Steam turbine units and lithium bromide equipment
Configuration yes, not examined in detail
2.2.6 Domestic supporting electrical cabinet
The devices are arranged in the equipment room, including: in the equipment room control room
and remote control room (1st floor of the office building).
Gabrielle Niu | Click here to see contact details in the message |
hi,we don't have this spurce now,if you can accept Chinese brand gas gen set,please add my whatsapp 86 186 3046 0723
ALireza Valadkhani | Click here to see contact details in the message |
Our company as one of the leading company as EPC power plant and gas generator supplier in our market , We are interested in your whole set of Jenbacher generators , would you please let me know the asking price and sale condition if still are available.
regards
Alireza Valadkhani
We use cookies to improve your experience. By continuing to use our site, you accept our Cookies, Privacy Policy,Terms and Conditions. Close X