PROJECT FACTS: MAK 12M282 Engine Output: 2400KW

img

PROJECT FACTS: MAK 12M282 Engine Output: 2400KW


PROJECT FACTS: MAK 12M282
Engine Output: 2400KW
RPM: 1,000 RPM
Main Bearing Pocket Diameter: 212 mm
Pockets Line Bored: 7 of 7

AUXILIARY ENGINE LINE
BORING AND MACHINING
END TO END RESTORATION OF MAK 12M282
CASUALTY

A highly specialized offshore support vessel in Houston
suffered a second catastrophic failure on one of its MAK
12M282 engines resulting in total loss on the blocks. Having
just been engaged to inspect and rebuild the first, Goltens
was engaged to perform the work on the second.
Goltens performed an inspection of the engines and
crankshafts and it was determined that the crankshaft could
be saved most economically by bench grinding in Goltens’
workshop and that the metal stitching would be cost
prohibitive and more economical to acquire a second hand
block. Complicating matters, both damaged engines were on
the same power bus and Goltens was engaged to relocate
one of the remaining operational engines to replace one of
the damaged engines to keep the ship operational while the
other two were being rebuilt.
The customer acquired two used blocks and engaged
Goltens in China to inspect one and Goltens in Dubai to
inspect the other. The blocks were then shipped to Goltens
in the US where the engines’ defects were corrected and
they were completely rebuilt.
On the second engine, it was determined that 5 of the 7
bearing caps needed to be replaced and that the engine
required line boring. Additionally, the 12 upper liner landing
surfaces needed to be machined. Goltens leveraged its insitu
technicians and flange facing and line boring equipment
to undertake the repairs prior to rebuilding the engine.
To finish the job, Goltens’ Diesel teams transported the
engine, rigged the engine onto the ship and into the engine
room and completed the installation and operational testing
of the engines.

REPAIRS CONSISTED OF:
• Inspection of damaged Engine and Crankshaft
• Disassembly and removal of engine
• Rigging and installation of operational engine to other
bus to keep ship operational
• Inspection of replacement block for suitability
• Bench grinding of crankshaft
• Straightening of damaged camshaft
• Laser bore alignment check of all main journal bores
• Line Boring of 7 of 7 main bearing pockets
• Flange facing of 12 upper line landing surfaces
• Reassembly of all engine components
• Rebuild of engine in Goltens workshop
• Transport, Rigging, Installation of rebuilt engine
• Completion of pre-start checks and operational run in of
the engine and operational testing of rebuilt engine.
RESULTS:
Goltens’ full spectrum of diesel and In-Situ machining
capabilities and its global network, enabled the customer to
deal with one company to complete inspections, overhaul,
machining and installation through the entire repair.
The vessel was kept in operation throughout the process and
was restored to full capability in a highly cost effective and
efficient manner.